Projects › Lyypäkki
WIND POWER PROJECT

Lyypäkki

Simo

The Lyypäkki wind power project is located in Simo. Nordic Generation is developing the project in cooperation with Metsähallitus. The project plans 42 wind turbines with an estimated total capacity of approximately 302 MW.

Technology
Wind power
Capacity
42 wind turbines (approx. 302 MW)
Development stage
Zoning proposal
Estimated timeline
Permitting 2027
Last mile project development 2028–2029
Construction starts 2029
Commercial operation 2030–2031

Project on the map

Lyypäkki project map
Enlarge map

Project progress

✓
Preliminary site studies
✓
Land lease agreements
✓
Draft zoning plan and EIA
Zoning proposal
Permitting and technical design
Last mile project development
Construction
Energy production
COOPERATION PROJECT

We are developing Lyypäkki together with Metsähallitus

Lyypäkki is a cooperation project between Nordic Generation and Metsähallitus. Metsähallitus is responsible for developing the project until the necessary permits enter into force, after which Nordic Generation will take the project forward towards implementation.

Learn more about the Lyypäkki project on the Metsähallitus website →
Nordic Generation × Metsähallitus

For landowners

We work with landowners on a long-term basis, from the first surveys all the way to energy production and site restoration.

Read more about our cooperation with landowners →